Basement Conversion Construction Stages
-
Week 1:
- Erect independent hording and access area to front of property.
- Create initial external opening (where possible) to the basement area and provide temporary weather- proofing and secure.
- Provide temporary supports where necessary.
- Supply external washroom facilities.
- Supply temporary electrics and water to basement area.

- Week 2 - 8:
- Remove soil, create a trench around the property perimeter, expose existing foundations and underpin where necessary.

- Week 9 - 11
- Once all underpinning is completed, excavate the bulk of the soil & dispose accordingly.

- Week 12 - 13:
- Cut into existing brickwork and prepare to receive structural steel bearing spreader plates.
- Install approximately 100 x 600 x 20 mm structural steel spreader plates to support steel beams.
- Install heavy duty steel beams ( RSJs ) and universal beams ( UB ) coated with intumescent coating to provide a minimum of 30 minute fire resistance.

- Week 14:
- Create new reinforced basement floor slab with damp proof membrane.

- Week 15 - 17:
- Supply and fix a cavity drain waterproofing system inclusive of base drain to slab, sump and pump for discharge (2 No. Submersible pumps with back-up alarm- basement Masters to supply.). and screed topping over membrane.


- Week 18 - 20:
- The construction and the formation of external light wells to front & rear of property where necessary.
- Approximate size 2M x 1M by approximately 1.8M deep with drainage and new windows to match existing windows above and metal railings around light well opening.
- A cat ladder to be installed in either light well as a secondary means of escape.

- Week 21 - 23:
- Dry line around the external wall perimeter, cavity to be filled with quilted insulation.
- Internal partitions are formed with the use of metal stud dry lining system or wooden stud partitioning (which ever is more suitable) filled with quilted insulation.
- Ceilings - new suspended ceilings to be constructed below existing floor joists, insulated with quilted insulation, finished with laminated plaster board with skim finished on exposed side to create a half hour fire rated ceiling.
- All first fix electrics and plumbing to be completed.
- Plaster board with 12.5mm and skim.



- Week 24 - 25:
- All existing doorways are temporarily sealed.
- Install new stairwell, closed tread softwood string staircase to provide access to converted area.
Complete all Second fixing: to include:-Electrics, plumbing, skirting, doors architraves.



- Week 26:
- Arrange final inspection with the Building Control Dept to have the works approved.
- Clear site and hand job over.
Completed Basements




Please note:- The dates and indications of the duration of the works are approximate. Some jobs may take longer, others may be quicker.