Basement Conversion Construction Stages

Week 1:
Erect independent hording and access area to front of property.
Create initial external opening (where possible) to the basement area and provide temporary weather- proofing and secure.
Provide temporary supports where necessary.
Supply external washroom facilities.
Supply temporary electrics and water to basement area.
Week 2 - 8:
Remove soil, create a trench around the property perimeter, expose existing foundations and underpin where necessary.
Week 9 - 11
Once all underpinning is completed, excavate the bulk of the soil & dispose accordingly.
Week 12 - 13:
Cut into existing brickwork and prepare to receive structural steel bearing spreader plates.
Install approximately 100 x 600 x 20 mm structural steel spreader plates to support steel beams.
Install heavy duty steel beams ( RSJs ) and universal beams ( UB ) coated with intumescent coating to provide a minimum of 30 minute fire resistance.
Week 14:
Create new reinforced basement floor slab with damp proof membrane.
Week 15 - 17:
Supply and fix a cavity drain waterproofing system inclusive of base drain to slab, sump and pump for discharge (2 No. Submersible pumps with back-up alarm- basement Masters to supply.). and screed topping over membrane.
Week 18 - 20:
The construction and the formation of external light wells to front & rear of property where necessary.
Approximate size 2M x 1M by approximately 1.8M deep with drainage and new windows to match existing windows above and metal railings around light well opening.
A cat ladder to be installed in either light well as a secondary means of escape.
Week 21 - 23:
Dry line around the external wall perimeter, cavity to be filled with quilted insulation.
Internal partitions are formed with the use of metal stud dry lining system or wooden stud partitioning (which ever is more suitable) filled with quilted insulation.
Ceilings - new suspended ceilings to be constructed below existing floor joists, insulated with quilted insulation, finished with laminated plaster board with skim finished on exposed side to create a half hour fire rated ceiling.
All first fix electrics and plumbing to be completed.
Plaster board with 12.5mm and skim.
Week 24 - 25:
All existing doorways are temporarily sealed.
Install new stairwell, closed tread softwood string staircase to provide access to converted area. Complete all Second fixing: to include:-Electrics, plumbing, skirting, doors architraves.
Week 26:
Arrange final inspection with the Building Control Dept to have the works approved.
Clear site and hand job over.

Completed Basements


Please note:- The dates and indications of the duration of the works are approximate. Some jobs may take longer, others may be quicker.